May the earth lie light: The Georgian cement crisis10 min read
Since 2017, laboratory blind tests have found that nearly two-thirds of bagged cement sampled on Georgian markets fails European standards. Yet since 2012 certification has been largely voluntary, and the country’s only clinker producer, part-owned by a fund launched by Bidzina Ivanishvili, is tested by no publicly named independent body. Drawing on deadly collapses in Batumi and Tbilisi, Venezuela’s 2026 earthquakes and the Roman epitaph sit tibi terra levis, this essay argues that Georgia’s danger lies not in deception but in the absence of anyone obliged to check.
Roman tombstones very often end with four letters: S T T L. They stand for sit tibi terra levis, “may the earth lie light on you”, and they were abbreviated for the same reason we now write RIP: everyone knew the words. It is the most common wish in Latin epitaphs, and it was meant more literally than it sounds. Beside it on the stones you find its relatives. There is a plea to the grave-marker itself, te, lapis, obtestor, leviter super ossa residas: “stone, I beg you, rest lightly on these bones.” The Romans thought about the dead in terms of weight. Their last kindness was to ask the ground, and the masonry, not to crush what lay beneath.
Not long ago, I spent a year writing a thesis on death in the epigrams of Martial, a first-century AD Roman poet better known for his obscenity than his grief. For Erotion, a child who died six days before her sixth birthday, he wrote: nec illi, / terra, gravis fueris: non fuit illa tibi. “Earth, do not lie heavy on her; she was never heavy on you.” I’ve thought about that couplet a good deal since I moved from reading Roman epitaphs to reading Georgian building registries. In Georgia, the prayer can seem to run the other way. Here it is not always the earth that lies on the dead. Sometimes it is the buildings that lie on the living.
On 14 July 2025, part of a five-storey residential building collapsed into the street near Station Square in Tbilisi. A man and a woman were killed, while a third person was taken to hospital. What stays with me is not simply that the building collapsed, but that authorities were already aware of its degradation. Tbilisi grades its failing housing on a five-point scale, using assessments by experts from the Levan Samkharauli National Forensics Bureau: categories one and two mean minor damage, three means significant structural damage, four means beyond repair, and five means virtually destroyed.
This building had already been graded category three. It had been reinforced once, in 2017, and it had since been designated an emergency. Its residents were offered a place in the city’s replacement programme, which only buildings graded three or above qualify for. Only two had accepted. Mayor Kakha Kaladze offered the classification by way of explanation: the city had made its offer, he said, but unanimous consent had not been secured.
Within days, the independent public servants’ union “Article 78 of the Constitution” raised its own questions. If the city had already classified the building as dangerous, why had commercial premises been allowed to operate inside it? Why had street trading continued in its shadow, and a car park been laid out in front? After the collapse, 102 residents were moved into eleven hotels. The Public Defender then returned to a much larger problem: thousands of people across Tbilisi are still living in buildings carrying the same classification.
The state had written the epitaph before the building had even fallen.
What Georgia is made of
One technical word matters for what follows: clinker. It is the essential intermediate material from which cement is made: limestone and clay are burnt at around 1,450 degrees into hard grey nodules, which are then ground, usually with gypsum and other additions, into the powder sold in bags. Much of cement’s strength begins with the quality and proportion of its clinker. One of the cheapest ways to make bad cement is simple: use less clinker and more of something cheaper. Buyers cannot see the difference. They rely on the assumption that somebody checked.
So what happens when somebody does? Since January 2017, the Georgian Cement Association has run a programme of blind tests. An independent purchaser buys bags anonymously in ordinary markets and sends them to two accredited laboratories, at the Samkharauli Bureau and the Georgian Technical University, to be measured against European standards. By mid-2022, almost four hundred samples had been tested. About a third passed. Nearly two-thirds failed.
The twelfth round, published in July 2022, used bags bought in eight towns, from Tbilisi and Rustavi to Kutaisi and Batumi. Of 32 samples, twelve passed. Of the twenty that failed, half could not reach 20 megapascals of compressive strength at 28 days, and six fell below 15. The European floor for the weakest ordinary class of structural cement is 32.5. A bag that tests below 15 is not a slightly inferior product; it is often a cheaper one, and on average failing bags sold for about a fifth less. After an earlier round, the association said some samples could barely be tested at all, being little more than inert material. All of it was on open sale, in a country that sits on active faults.
The association’s provenance deserves a plain sentence. It is an industry body, and its reading of the results—that the failing cement comes mostly from small local mills grinding imported clinker—happens to suit the commercial interests of the country’s only domestic clinker producer. That is a reason to attribute its findings carefully, not to dismiss them. The laboratories are not the lobby, and the results have been published round after round since 2017.
Much of this is legal, or close enough. In 2012, Georgia adopted the Product Safety and Free Movement Code, part of a broader drive to strip back pre-market regulation. Mandatory certification for most construction materials was largely dismantled. The Georgian National Agency for Standards and Metrology adopts and translates European norms, but for most building materials conformity is now voluntary or declared by the importer. The market was set free, and the buildings were set free along with it.
The producers
Who makes the cement? For seventeen years the answer had a German flavour. HeidelbergCement entered Georgia in 2006, invested more than €200 million over the following years and ran, most importantly, the only clinker production in Georgia. Every other cement producer in the country grinds clinker that somebody else made.
In November 2017, HeidelbergCement sold 55 per cent of its Georgian holding company for €20.8 million in cash to Cement Invest B.V., a Netherlands-registered vehicle jointly owned by the Georgian Co-Investment Fund and Hunnewell Partners, the private-equity firm of Irakli Rukhadze. The Co-Investment Fund had been launched by Bidzina Ivanishvili in September 2013. In 2023, Heidelberg sold its remaining 45 per cent to Cement Invest and left Georgia, and the following year the company became Hunnewell Cement. The plants stayed where they were.
An investigation by Radio Free Europe/Radio Liberty with the environmental organisation Green Alternative found that the Georgian business had operated at a loss for years until the new owners took control, after which it recorded more than 100 million lari in profit over three years. The same investigation found repeated environmental violations across the company’s facilities, including complaints from villagers near its limestone quarry who blame blasting for cracks in their homes, answered with a handful of fines the reporters described as meagre.
In May 2026, with Prime Minister Irakli Kobakhidze in attendance alongside Rukhadze, the company broke ground on a $70 million expansion at Kaspi: a new clinker line and grinding plant that will lift clinker output to two million tonnes a year by 2028, presented as a way of reducing the country’s dependence on imports. I have been unable to find, in any public document, who is building the new line, to what standard its clinker will be certified, or which independent body, if any, will test what comes out of it.
So the market looks like this. At the edges, small mills grind imported clinker, much of it from Azerbaijan, into bags that fail laboratory tests two times out of three; fifteen of the twenty failures in 2022 came from exactly such mills. At the centre is a single producer, connected to the highest levels of Georgian political life, whose product is tested by nobody the public can name. The edges are measurably bad. The centre is simply unmeasured.
When buildings fail
While this was going on, the country kept a second set of accounts.
On 8 October 2021, one entrance of a residential building on 26 May Street in Batumi collapsed late in the morning. Nine people died, three of them children, the eldest twelve; four of the dead were from one family. Investigators said load-bearing walls had been dismantled during renovation of a flat on the lowest floor, work its owner had begun before his permit application was approved. The Interior Minister, Vakhtang Gomelauri, stood at the site and said that illegal extensions were a problem throughout Georgia, and that he did not know what the government should do about it. It was a regulatory vacuum, describing itself at the scene, in the words of the minister responsible.
And then there are the years that no single disaster makes visible. The Labour Inspection Service recorded 39 workplace deaths in 2020, and a slow decline to 32 in 2025. It looks like progress. It also means that more than three hundred people have died at work in Georgia in the past decade, with construction consistently the deadliest sector. Of last year’s 32 dead, 21 were on building sites.
What this looks like at scale
The obvious objection is that none of this adds up to a catastrophe. Georgia has had tragedies, not a disaster. That is true, and it is the argument I find least reassuring, because we have just watched what the difference looks like.
On 24 June this year, two earthquakes struck northern Venezuela within a minute of each other, the second of magnitude 7.5 off the coast of La Guaira. By August, more than 6,500 deaths had been officially confirmed, and tens of thousands of people were still listed as missing. Much of the worst destruction was in public housing towers built under the government’s Gran Misión Vivienda [Great Housing Mission], launched in 2011.
In 2008, the Venezuelan state nationalised its cement industry. From 2009, according to a member of the country’s College of Engineers, the professional body that had overseen public construction tenders was progressively shut out of that role. In 2017, the then president of the College of Engineers described the structural integrity of the government-built units as a state secret. For more than a decade, residents and seismologists publicised cracks in the walls and warned that the towers might not survive a large earthquake.
Georgia is not Venezuela, and I am not suggesting it is. The lesson I take is narrower, and administrative rather than seismological. When the state stops asking what its buildings are made of, and discourages anyone else from asking, it does not avoid the answer. It receives the answer all at once. How many Georgians live or work inside cement that would fail a laboratory test? Nobody can say, because nobody has been asked to find out. In an earthquake, some of those people may be hurt or killed.
The underlying cycle
I spent more time with Martial’s sixth book than with any other. It opens with the emperor Domitian as builder, celebrating tot nascentia templa, so many temples being born across Rome. Then, poem by poem, it quietly fills with deaths. Georgia’s construction record reads the same way. The groundbreakings are televised; the registry of condemned buildings is not.
Reading Martial also taught me that an absence can be the loudest thing on the page. There is no villain here holding a forged certificate, because there are hardly any certificates to forge. There is no cover-up, because nothing is hidden. What is missing is the obligation to verify. A system that never promises verification can never be caught breaking the promise. Since 2012, deregulation has been load-bearing.
The Romans asked the earth to lie light on their dead because there was nothing else left to ask. We are not yet in their position. We are the living, standing inside the buildings, and we are entitled to one plain question: who tests our cement, and to whose standard? It is a small question. So is a crack in a stairwell.